Investigate a supplier delay

Trace a five-day bearing delay to orders, compare stock and make a governed proposal.

Kaeshin Data Platform · For workspace admins and business teams

An illustrative five-day delay

A precision-parts factory receives a notice that supplier S-118’s bearings will arrive five days late. The question is not just “Which supplier is late?” It is “Which production and customer commitments might be affected, what alternatives exist, and who may authorize a change?” This is a worked investigation plan, not a report from a live factory connection.

Before starting, the published model needs Supplier, Material, Production order, Customer order and Warehouse stock types, suitable dates and quantities, and explicit relations: Supplier supplies Material; Production order requires Material; Production order fulfills Customer order; Warehouse stock holds Material. Your organization chooses the actual names. Populate the records and links manually or through mapped pipelines; these are not built-in factory presets.

Establish the facts and the route

  1. In Records → Table, choose Supplier and search S-118. Open the exact record, check its identifier, delay evidence and expected arrival. Check the relevant pipeline’s latest data time if the record comes from a source.

  2. Ask the assistant: “Find the supplier, material, order and stock definitions, then explain the fields and relation directions we should use.” This combines finding concepts with reading their definitions.

  3. Ask: “Find S-118 and show the bearing materials it supplies. Follow the requirement relation to open production orders and then their customer orders. Show counts and read all relevant results, not only the preview.”

  4. Open selected records and their Links or Open in graph to verify the path. Compare the delayed arrival with required material dates and planned completion. Identify an exposure to review; do not assume a relation automatically proves a missed customer delivery.

Compare an alternative with the demand

Ask the assistant to follow the bearing Material to Warehouse stock and summarize available quantity by warehouse. Separately summarize required quantities for the affected production orders. State the unit and compare stock times. Check whether “available” already excludes reservations; do not subtract them twice or mistake total on-hand for usable stock.

For illustration only, suppose the records show 120 usable bearings in another warehouse and an affected order needs 80 of the same bearing specification. Those numbers make an 80-bearing reassignment a candidate. They do not establish quality approval, transport timing or another order’s entitlement. Read those facts where modeled and ask the responsible people where they are not.

Keep missing quantities visible as unknown. A grouped total can count a record more than once if it belongs to several groups. Inspect the underlying stock entries and order requirements before presenting a recommendation.

Preview the proposal and obtain approval

The published Reassign stock action must already define the required inputs, stock and order checks, exact relation or quantity changes, and any outside-system work. Review it in Schema → Actions. If the action does not exist, have an authorized model author create and test it; an assistant cannot improvise an approved operation from a name.

Ask for a preview only, naming the exact production order, stock entry and illustrative quantity of 80. Review the proposed changes and any blocked conditions. If Governor requires approval, follow the created request under Approvals → I asked. Eligible approvers review the same proposal in To sign. A caller’s confirmation is separate from their signatures; a required decision must also be satisfied.

After authorization, use the offered execution flow for the reviewed proposal. If the stock, order or inputs have changed, re-check before running. An approved proposal should not silently expand to more orders or a different warehouse.

Verify the outcome and communicate its limits

Open the action run in Actions → History. Check saved changes, failures and any Waiting for the source state. Reopen the production order and stock records, then check their History and current links. If the action updates an outside warehouse system, wait for the required confirmation or investigate disagreement.

The useful outcome is a traceable proposal and a checked result: which customer orders were examined, which stock was selected, who authorized the change and what actually happened. Updating a stock allocation does not itself promise a customer date. Communicate the verified change and the remaining transport, production or customer confirmation work explicitly.

✳